"Vulcan aimed to triple met coal production at Moatize in 14 months. With 17 brownfield projects identified, including 2 thickener projects, Realization's Focus-&-Finish method streamlined execution. By prioritizing one project at a time, Vulcan achieved efficient results, with the first project completed in 260 days (vs. 340 days projected) and the second, with expanded scope, in just 135 days. Shutdown tie-ins were also completed punctually."
Mr. Rajender Tiwari
,
Executive Vice President
Vulcan International