Brahmani River Pellets Limited (JSW Group and Thriveni Group are its present joint promoters) is one of the largest merchant pellet manufacturers in India, with a pellet manufacturing capacity of 4 MTPA at its Jajpur plant, supported by a beneficiation capacity of 4.7 MTPA at its Barbil plant.
Challenges:
When BRPL decided to upgrade their Barbil beneficiation plant by adding six HGMS (high-gradient magnetic separation) system to the circuit to increase Fe recovery from the tailings and allow lower grades of raw material to be used, they faced several challenges:
Additional challenges encountered during the project included:
Implementation:
Having seen operational benefits from Realization’s Critical Chain solution in a previous engagement with Tata Steel, the management was keen to explore the same approach for the current upgrade. Once Realization Technologies was brought on board, they took less than two weeks for the initial analysis and setup phase to:
After receiving the go-ahead, the team quickly moved to the execution phase to:
Tangible Results:
Intangible Results:
Client Testimonial:
“Realization Technologies proved instrumental in upgrading our Barbil beneficiation plant with the addition of an HGMS(high-gradient magnetic separation) system. Within just two weeks of engagement, they created a comprehensive project plan, aligned timelines & processes with all stakeholders. Their proactive identification of risk areas and mitigation strategies set a solid foundation for success. Today, we are well on our way to complete the project within the original timeline of 14 months.
With their unique multi-tiered planning approach, we maintained control of execution and remained confident in achieving our targets. The Focus-and-Finish methodology provided clear guidance for teams, empowering us to execute projects with minimal manual coordination.
Streamliner is easy to understand & adapt to in project environments.”
PR Prasad - Director Steel - Lloyd Metals & Energy Ltd.(Ex MD - BRPL)
Conclusion:
With the unique multi-tiered planning in Streamliner, the team maintained control over the execution and remained confident about achieving the targets. Strict adherence to the Focus-and-Finish approach acted as guardrails for the team, enabling them to work in a near-autonomous mode with minimal management intervention. By using the live overall project picture– the workstream view – early warnings were identified and acted upon proactively, ensuring unnecessary delays were avoided.
In the end, the project was completed within the original timeline of 14 months.
Plant shutdown needed for HGMS upgradation.
Timeline pressure to recover Fe and enable RM.
Delays in engineering, ordering, and equipment delivery.
Civil manpower shortage affected execution.
Focus-&-Finish plan in two weeks.
Mapped processes, identified risks, prioritized engineering.
Enabled decision making on workstreams & created what-if scenarios for shutdown planning.
Staggered commissioning of HGMS for minimal disruption.
Timeline and risks established within two weeks.
Lead time reduced by loaning HGMS units.
Staggered HGMS commissioning minimized disruptions.
Project completed within original 14-month timeline.