Six Months to Commission a 72-Meter Mill: Jindal Sohar Execution Turnaround
Case Summary
- 01
Challenges
- Project completion date was slipping repeatedly with no stable commissioning target.
- Multiple major scopes were running in parallel in a highly constrained working area.
- Common crane movement zones created frequent clashes and daily coordination issues.
- Structural manpower was lower than required for the remaining scope.
- Commissioning teams were spread across several partially completed systems.
- 02
Our Work
- Reviewed remaining scope, site constraints, manpower, and system dependencies.
- Defined a clear priority milestone: commissioning of Dry Mill-1.
- Stopped Dry Mill-2 erection and redirected resources to off-site readiness.
- Dedicated site access and cranes exclusively to Dry Mill-1.
- Reorganized commissioning to close systems one by one.
- Enforced full-kitting before releasing work fronts.
- 03
Results
- Completed Dry Mill-1 erection and first-stage commissioning in six months.
- Delivered two months faster than typical industry timelines.
Situation When Realization Was Engaged
In May 2025, Realization was called into the Jindal Steel Sohar (JSS) Pellet Project when the project had entered a difficult phase. The completion date had been moving repeatedly, typically slipping by about two months at a time, and there was no longer a clear or predictable end point.
By then, a large amount of work had already been done. Both Dry Mill 1 and Dry Mill 2 were under erection. Conveyor systems were about 50% complete. Commissioning activities had started on multiple units. However, despite visible progress, the project was not converging toward any stable commissioning milestone.
Structural manpower availability was also constrained. The requirement was assessed at around 120 structural manpower, while mobilization was closer to 90.
More critically, several major scopes were competing for the same physical space. Dry Mill 1 and Dry Mill 2 shared the same access routes, crane movement zones, and material storage areas. Although separate erection contractors were engaged, key resources such as piping teams and heavy lifting equipment were common. This created daily coordination issues, crane clashes, and frequent start-stop situations across all fronts.
Execution Analysis and Target Definition
Realization carried out a focused execution analysis jointly with the JSS team.
Based on the remaining scope, physical constraints, structural manpower availability, and system interdependencies, an aggressive but feasible objective was defined: achieve first-stage commissioning of Dry Mill 1 by October 2025 (16 Months).
This milestone was selected to create a clear convergence point for execution and to stabilize priorities across the site.
Key Execution Decisions
Three core execution decisions were taken to support this objective.
1. Resolving the Area Constraint
All erection work on Dry Mill 2 was stopped. Its contractor was redirected to off-site fabrication and readiness activities. The entire site access, crane capacity, and working area were then dedicated to Dry Mill 1. This immediately removed crane clashes, reduced daily coordination dependency, and enabled uninterrupted progress on the heavy structure. The focus was maintained until the major structural lifts of Dry Mill 1, including heavy lifts up to around 30 meters, were completed.
2. Refocusing Commissioning Effort
Commissioning teams, which were earlier spread across multiple systems, were reorganized. Instead of opening many parallel fronts, teams were aligned to complete and stabilize units one by one. The objective was to close systems fully before opening new ones, rather than carry multiple partially commissioned units.
3. Establishing Full-Kitting Discipline
Full-kitting was enforced across ducting, conveyors, and ESP scopes. Work was not started unless drawings, materials, access and manpower were ready. This significantly reduced routine start-stop losses and allowed crews to execute scopes without repeated interruptions.
Execution Outcome & Result
With these changes, execution began to stabilize. Although the October target could not be fully achieved, the balance scope was completed in November 2025. Dry Mill 1 erection and first-stage plant commissioning were achieved within roughly six months from Realization’s entry into the project. Considering the scale of the structure (approximately 72 meters) and the parallel commissioning scope, this outcome was materially faster than typical industry timelines, which generally require eight months or more for similar erection and commissioning.
Realization India supported us in project controls during the execution of the Jindal Steel Sohar Pellet Project and played an important role in helping us complete the project as per the committed timelines.
The Realization team worked closely with our site and project teams to identify key constraints and remove them through decisive and collaborative planning. The introduction of full-kitting discipline significantly improved overall work flow at site. Their contribution had a clear and meaningful positive impact on the project.
Mr. Vimal Malhotra
Contact us to find out more
Our Customer Service Teams have hundreds of Industry specific studies to draw from ... get in touch if you want to see something specific to your needs, or simply explore how we can deliver Radical Results for you.
.png)



